Factory Audit Before You Place the Order

One day on site, one report that tells you whether the factory can make your part the way its sales office says it can. We check the floor, the machines, the QC system and the paperwork, photograph everything and flag the risks. Report within 5 working days.

When to audit

Before the first PO, before a bigger one, or after a bad lot

  • A new supplier found at a trade show, on Alibaba or by referral, before the first purchase order
  • An existing supplier before you move from samples to volume, or from one part number to a family
  • After a failed lot or a missed date, to find out whether it was a one-off or the system
  • A factory that claims a process you have never seen it run
What we check

Six areas, on the floor and in the files

Facility and equipmentMachines against the list the factory sent you, age and condition, maintenance records, measuring equipment and its calibration
Capacity and loadShifts, headcount on the line, current orders on the floor, realistic lead time for your quantity
QC systemIncoming, in-process and final inspection in practice, not only on paper; who signs what; how a non-conformance is handled
Document trailMaterial certificates, inspection records of a recent order, traceability from material lot to shipped carton
Capability against the claimThe process you need, done on the floor by their own people, or subcontracted out of sight
Export readinessPacking, labelling and export documents from a recent shipment to your market
What you receive

A report you can act on without a call

Each area gets a finding, a photo and a risk flag: red, amber or green. The last page is a plain verdict on your part and your quantity, the open questions to put to the factory, and what we would watch on the first order if you go ahead.

Audit reportExample format

Factory
Name withheld, Dong Nai, aluminium machining and anodising
Part and quantity
Housing, 6 part numbers, 1,800 pcs per month
Equipment
Matches list sent; two of nine machining centres idle, one CMM calibrated 2025
QC system
Final inspection records kept; in-process check sheets not used on two lines
Document trail
Material certificates on file; lot traceability stops at machining
Capability
Anodising subcontracted to a plant 40 km away, not disclosed in the quote
Risk flags
Amber: in-process records. Red: undisclosed subcontracting
Verdict
Suitable for the first PO with in-line visits at first article and before anodising
Photos
64 attached

Illustration of the format. Not a report on any real factory.

Contract

One audit, one contract

One day on site for most factories, two for a plant with several processes. Scope, travel and fee are set in the contract before the visit. If you go on to order control, the audit becomes its baseline.

FAQ

Questions about audits

Is this a social compliance audit?

No. This is a quality and capability audit: can this factory make your part to your drawing, on time, with records to prove it. For amfori BSCI, Sedex SMETA or similar, we point you to an accredited audit body and can coordinate the visit.

Will the factory know who the buyer is?

Only if you want. Most buyers introduce us by name as their quality contact. For a factory you have not committed to, we can audit as a prospective buyer’s representative without naming you.

Can you audit a factory I have not contacted yet?

We need an introduction from you first. We do not visit factories unannounced or on our own initiative.